On May 27, 2026, M.T. Shamyrkanov, Head–Akim of the Chon-Alai District State Administration, inspected the repair work on the Ming-Jar Canal in Achyk-Suu village in accordance with an instruction from the President of the Kyrgyz Republic, Sadyr Japarov.
The Chon-Alai District Development Fund allocated 6,700,000 soms for the project. Excavation work is currently being carried out along a 6.5-kilometre section of the canal, while construction of the GVS dam is also actively underway.
Main objectives
- provide irrigation water to land that previously lacked a sufficient water supply;
- bring unused land into agricultural production;
- create favourable conditions for local farmers;
- increase the district’s agricultural potential;
- contribute to the area’s social and economic development.
Funding source
Chon-Alai District Development Fund
Project budget
6,700,000 soms
Work underway
- excavation along a 6.5-kilometre section of the canal;
- construction of the GVS dam;
- restoration and improvement of the irrigation system.
Expected results
Once the project is fully completed:
- 1,400 hectares of land will be supplied with irrigation water;
- previously unused land will be brought into productive use;
- better conditions will be created for local farmers;
- agricultural production will increase;
- the project will make a significant contribution to the district’s development.
Project status
In progress
Project location
Achyk-Suu village, Chon-Alai District
Key indicator
1,400 hectares of land will be supplied with irrigation water